- The agreement covers 200 megawatts of capacity deliverable to the grid.
- Axian estimates annual output of around 530 gigawatt-hours.
- The agreement secures an intended buyer while finance, construction and delivery remain separate milestones.
Inside this story 2 perspectives
One of the first questions a lender asks about a new power station is who will pay for the electricity. Zambia’s planned Kudu solar plant now has an answer. Africa GreenCo announced on 8 October that it had signed a power purchase agreement with Axian Energy. The proposed generator gets one buyer, a company that can in turn sell electricity to a range of customers across Southern Africa.
The figures attributed to Axian by Bankable give the project three quite different sizes. The solar equipment is expected to have a peak capacity of 240 megawatts. The agreement covers 200 megawatts deliverable to the grid. Annual energy production is estimated at about 530 gigawatt-hours. The first two figures refer to power at a point in time. The third describes how much electricity might be generated over a year, as sunlight and operating conditions vary.
A buyer with somewhere else to sell
For a developer, an agreement covering future output makes anticipated revenue easier to explain to lenders. If the electricity can only be sold to one local utility, its ability to pay becomes a central part of the financing decision. GreenCo acts as an intermediary. It agrees to buy electricity from independent producers and seeks customers in a wider market, including utilities and commercial users. The generator can deal with one counterparty while that counterparty manages the relationships further down the line.
GreenCo has experience arranging cross-border supplies in a period of tight Zambian electricity availability. In an earlier announcement with Stanbic Bank it described using prepayment facilities to support regional electricity transactions. Kudu addresses the supply side from the opposite direction. Instead of only seeking existing electricity for customers that need it, the trader’s purchase agreement gives a proposed source of new generation a route to those customers.
A contract and a physical connection
A trader’s portfolio can span national borders more easily on paper than electricity can traverse them on the grid. A cross-border sale also needs transmission capacity and arrangements to move the power over the relevant networks. Mining operations in the Democratic Republic of Congo are among the possible regional customers discussed in coverage of the deal. No specific purchase by a Congolese mine was announced in the 8 October report.
Axian already has a presence in Zambia through the Bangweulu solar plant. Kudu would substantially expand that presence if it reaches operation. The new agreement is evidence of a willing buyer for a much larger project. It will take financing, construction and actual deliveries before the projected 530 gigawatt-hours can be compared with an annual meter reading. For now the most consequential change is the answer to the lender’s question. It names a regional trader, opening up a larger set of potential customers than the project could reach on its own.