THE STORY IN BRIEF
  • Government will consult the seven pre-qualified bidders again before issuing a final request for proposals.
  • A second draft is due before the end of 2026, with a draft non-binding credit-guarantee term sheet expected alongside it.
  • The revised target for a final request is the second quarter of calendar 2027.
MAKE TIME FOR A GOOD READ
Inside this story 2 perspectives

A company asked to build and finance a transmission line cannot sensibly quote a price until it knows which risks it will carry. Will it receive the agreed payment if a delay occurs beyond its control? Which obligations are supported by a guarantee, and which remain with the company and its lenders? South Africa is giving seven pre-qualified bidders another opportunity to examine those questions before it asks for binding bids.

Under the revised timetable reported on 2 October, government plans to issue a second draft request for proposals for the first phase of its Independent Transmission Projects programme before the end of this year. A final request is now targeted for the second quarter of 2027. The earlier timetable had envisaged issuing that final request no later than the third quarter of 2026.

Why the next document is still a draft

The further consultation is confined to the seven pre-qualified parties. It follows an initial round of discussion and is intended to let potential bidders and their lenders inspect a more complete set of documents together. Government says the second draft is expected to be accompanied by a non-binding term sheet outlining the proposed credit-guarantee arrangements.

The word non-binding matters. A draft can show which risks a guarantee is intended to cover and where its boundaries might lie. A lender deciding whether it can finance a particular bid will ultimately need final terms. If the obligations in a guarantee do not match the obligations in the main project contract, a bidder may have to allow for the gap in its price or decide it cannot participate.

Being pre-qualified is also distinct from winning the project. It identifies parties allowed to proceed in the competition. It does not tell businesses which contractor will build a line or entitle an investor to a future stream of payments.

The cost of changing the timetable

Another draft adds time before bids can be assessed. It can also expose a provision that several lenders would otherwise reject only after companies have spent considerable sums preparing proposals. The government’s argument for the change is that the structure of this first procurement is likely to influence later private investment in the grid. Whether the extra round produces a more workable agreement will become clearer in the final documents and the bids they attract.

For a power developer waiting for a connection, a procurement milestone is not a date on which new grid capacity will become available. There are still approvals, bids, financing decisions and construction between the two. The announcement nevertheless makes one part of the sequence clearer. Before South Africa can compare prices from the seven parties, it intends to give them the same, more complete picture of what they are being asked to finance.

BB